Asphalt Concrete Laying, RCC Hume Pipe Laying, Footpath and Road Development Works etc.

Project Manager

Name: Ajit Khanal

Project Status
0%
20/12/2017 14/01/2020

Complete

Project Detail:

Asphalt Concrete Laying, RCC Hume Pipe Laying, Footpath and Road Development Works etc.
Asphalt Concrete Laying, RCC Hume Pipe Laying, Footpath and Road Development Works etc.
Dhobikhola Corridor Improvement Project, Anamnagar, Kathmandu
DCIP/074/75(KP-KBP)-01
Anamnagar
20/12/2017
20/12/2017
217,441,969.70

Progress Pictures