2023-09-17

Extension of Imadol-Siddhipur-Godawari Khola-Lubhu Lamatar Road

2022-03-27

Project Manager

Name: Ajit Khanal

Cell: 9849142739

E-mail: aj.khanal22@gmail.com

Project Status

Physical
0%
17/07/2017 15/10/2022
Financial
0%
17/07/2017 15/10/2022

Complete

2023-08-07

Project Detail:

Extension of Imadol-Siddhipur-Godawari Khola-Lubhu Lamatar Road
Extension of Imadol-Siddhipur-Godawari Khola-Lubhu Lamatar Road
Kathmandu Valley Road Improvement Project
KVRIP/3371494/073/74/006
Imadol-Siddhipur-Godawari Khola-Lubhu Lamatar Road
17/07/2017
17/07/2017
63 month
459,032,002.12

Progress Pictures